Make up days due to weather

What do the contracts say about weather conditions and make up days?

WWA AGC – Article 16 (b) …… in the event the job is down due to weather conditions. or other conditions beyond the control of the employer, Monday through Friday, then Saturday may, at the option of the Employer, be worked as a voluntary make-up day at the straight time rate.

OR/SWWA AGC – Article 6 …… Five Eight -Hour Shift (5-8).  In the event the job is down due to equipment breakdown or weather conditions, Monday through Friday, Then Saturday on a voluntary basis may be worked as a make-up day at the straight time rate.

Inland NW AGC – Article 16 ……  It is suggested to read this entire article from 16.1 to 16.6.

NW Wall & Ceiling – Article 11.01 (b) ……In the event the job is down due to weather conditions, or other conditions beyond the control of the Employer, Monday through Friday, the Saturday may, at the option of the Employer, be worked as a voluntary make-up day at the straight time rate.

These options listed are for Monday through Friday shifts.  There is similar language in each contract concerning 4-10’s.

Did You Know?

Carpenters skills and training go beyond the job site.

The Journeyman Leadership Program is a three day program geared towards developing the strong qualities of members on the job and in their lives – leadership, communication, mentoring and collective action. Members learn where the UBC came from and where its headed, and, importantly, how to lead it. Learn More

X

Sign up for mobile alerts

Mobile alerts from Northwest Carpenters. Periodic messages. Msg & data rates may apply. Text STOP to 91990 to stop receiving messages. Text HELP to 91990 for more information.
Terms & Conditions